| Order from | Rewa Ultra Mega Solar Limited |
| Execution period | SCOD 31 December 2027; 25-year tenure from PPA signing |
Key highlights
- Agreement covers a 220 MW solar project integrated with a Battery Energy Storage System (BESS)
- Project located at Morena Solar Park, Madhya Pradesh, designated as Unit II
- Power Purchase Agreement (PPA) features a fixed tariff of Rs. 2.764 per unit
- Scheduled Commercial Operation Date (SCOD) is set for December 31, 2027
- Contract tenure extends for 25 years from the date of PPA signing
A 25-Year Energy Agreement With Rewa Ultra Mega Solar
Acme Solar Holdings Limited has formalized a long-term Power Purchase Agreement (PPA) through its wholly owned subsidiary, ACME Greentech Sixteen Private Limited. The contract, signed with Rewa Ultra Mega Solar Limited (RUMSL), outlines the development of a 220 MW solar power plant enhanced by a Battery Energy Storage System (BESS). Located in the Morena Solar Park in Madhya Pradesh, the project is structured to supply energy at a competitive tariff of Rs.
2.764 per unit. The agreement ensures a stable revenue stream for the company over a 25-year operational lifecycle, with full commercial operations targeted for December 31, 2027.
Robust Financial Performance Precedes Project Execution
The new order follows a period of strong financial growth for ACME Solar. In the quarter ended September 30, 2026, the company reported operating revenue of ₹887.01 Cr, reflecting an 89.63% year-on-year increase. Net profit for the same period reached ₹268.4 Cr, up 133.24% compared to the previous year.
The company maintained a high operating profit margin of 84.94% during this quarter. With an annual net profit of ₹498.92 Cr for the 2026 fiscal year and significant cash flows from operations, the firm remains well-capitalized to execute its expanding pipeline of storage-backed renewable energy projects.
Strategic Expansion of the Contracted Portfolio
- Total contracted capacity reached 8,370 MW as of September 30, 2026, including operational and under-construction units
- Recent 400 MW ISTS-connected FDRE project PPA signed with NTPC Limited on October 28, 2026
- Execution of 300 MW assured peak supply project PPA with SECI in October 2026 via ACME Greentech Twenty
- Two 25-year PPAs previously signed with SJVN for 450 MW storage-backed projects in March 2026
- Management has upgraded FY27 battery storage commissioning guidance to over 12 GWh from an initial 10 GWh target
| Date | Announcement | Amount |
|---|---|---|
| 28 Oct 2026 | Execution of 25-year PPA with NTPC Limited for 400 MW ISTS-connected FDRE project under FDRE Tranche-01 by subsidiary ACME Marigold UrjaSource: BSE filing | – |
| 19 Oct 2026 | Execution of PPA with SECI for 300 MW / 1,200 MWh assured peak supply project under FDRE-IX tranche by subsidiary ACME Greentech TwentySource: BSE filing | – |
| 28 Aug 2026 | Receipt of Letter of Award from SECI for 300 MW contracted capacity under 6,000 MWh Assured Peak Power Tender (FDRE-IX)Source: BSE filing | – |
| 21 Jul 2026 | Execution of PPA with SECI for 300 MW ISTS-connected Wind-Solar Hybrid project under Hybrid Tranche IX by subsidiary ACME Renewtech FifthSource: BSE filing | – |
| 12 Mar 2026 | Execution of two 25-year PPAs with SJVN for 450 MW / 1,800 MWh storage-backed assured peak power project by subsidiary ACME Greentech SeventhSource: energetica-india.net | – |
| 30 Jan 2026 | Execution of 25-year PPA with NHPC Limited for 250 MW ISTS-connected FDRE Tranche-VI project by subsidiary ACME Urja OneSource: BSE filing | – |
What to watch next
- Full commissioning of remaining solar capacity at the Bikaner hybrid plant by December 31, 2026
- Progress on the 1.2 GW under-development pipeline awaiting PPA tie-ups as of late 2026
- Scheduled Commercial Operation Date (SCOD) for the Morena solar-BESS project on December 31, 2027
- Advancement toward the 2030 goal of 15 GW generation capacity and 50 GWh battery storage capacity
| Share price | ₹402.4 |
|---|---|
| Market capitalisation | ₹28,444.62 Cr |
| Revenue (annual) | ₹2,023.38 Cr |
| Net profit (annual) | ₹498.92 Cr |
| Revenue (latest quarter) | ₹887.01 Cr+3.44% vs previous quarter |
| Net profit (latest quarter) | ₹268.40 Cr+14.05% vs previous quarter |
| P/E (TTM) | 37.59×Sector 21.51× |
| Promoter holding | 71.4%0.00% QoQ |
| FII holding | 6.44%Current quarter |
Reference market data from a third-party provider, as of the story. Not a valuation or a recommendation.
Exchange filing by Acme Solar Holdings Limited announcing the execution of a Power Purchase Agreement with Rewa Ultra Mega Solar Limited. Market figures from a third-party data provider.